Grouped Asset PMs are scheduled PMs that enable you to create one PM record with separate schedules for each Group and its Assets. These PMs will generate one Work Order for each Group based on the Group's individual schedule. Each Work Order will also contain the Group's Assets.
Capabilities
Contains multiple groups.
Each group will have one or more assets and a schedule that can be based on:
Fixed Scheduling
Floating Scheduling
Will create a single Work Order per schedule that contains the assets from the related group.
Example uses
In a pump inspection program, each pump needs to be inspected bi-annually, but they should be inspected with the other pumps in the same pump station. The same tests, crews and resources are used on each inspection, but the work should be spread out so the inspections are in different months.
Note: The Add GroupsToolkits require you to add an Asset that will appear in the PM Grouped Assets grid. Assets can be added, deleted or editedin the PM Grouped Assets grid.
Click the to expand a PM Group.
In the Group's Grouped PM Scheduling grid, click the Toolkit and select Add New Schedule to set the Group Schedule. Repeat for each Group that needs a Schedule. More information on PM Group Scheduling.
Now that the PM is set up and has Groups, Assets and Schedules, the PM will generate one Work Order for each Group and its Assets the next time each Group's Schedule is triggered.