Labor Days Tab

The Labor Days tab tracks the estimated number of labor days to complete all Tasks related to the Department as well as the actual number of labor days spent on Work Orders in the system. All of these fields are automatically calculated.

Field Name

Definition

Est Labor Days

per month

Shows the estimated number of labor days required each month to complete the Tasks associated with this Department. This is the sum of the corresponding Est Labor Day fields from all of the related Planning Tasks > Labor Days tab.

Actual Labor Days

per month

The actual days of work the department accomplished. This is the sum of the corresponding Actual Labor Day fields from all the related Planning Tasks > Labor Days tab.

Est Labor Days: TOTAL

The sum of all the Est Labor Days fields.

Actual Labor Days: TOTAL

The sum of all the Actual Labor Days fields.

% Labor Days YTD vs Planned

This field calculates how much of the planned work remains for the Fiscal Year. The estimated amount is compared with the quantity of task asset units completed in actual work orders each month.

See Also

Department

Department Header Data

Status Tab

Tasks Tab

Availability Tab

Costs Tab

Custom Tab(s)

Comments Tab

Toolkit