The second tab of the TV Observations record appears below. This tab contains additional fields used to rate the observation and defects found. For a description of these fields, refer to the table below:
Field Name |
Description |
Estimated GPM |
The estimated flow rate is a default value assigned from the Inspection Setup table. |
Structure # |
The program automatically assigns the structure number from the Inspection Setup table. |
Cleaning # |
The program automatically assigns the cleaning number from the Inspection Setup table. |
% I/I Removed |
Use this field to record the percent of infiltration and inflow that was removed due to the rehabilitation. |
Remaining GPM |
This field allows you to record the amount of flow remaining after rehabilitation. |
Repaired |
This field allows you to indicate the type of rehabilitation performed. |
Min Rehab Priority |
This field is used to indicate the rehabilitation priority. The Sewer Rehab model will refer to this priority value when determining whether to select a defect for rehabilitation or replacement. |
Rehab Method |
This field is used to indicate which rehab method should be used if this defect is selected for rehabilitation or replacement in the Sewer Rehab model runs. |
Rehab Cost |
This field is used to indicate the rehab cost for the observed defect. If a value is included in this field, it will be used in the Sewer Rehab model runs. If no value is included, the model runs will use their own default calculations. |
User |
These user-defined fields allow you to include additional, custom information. |