Modify Stop

Complete the following steps to modify the end date for a work order or task:

  1. Click edit to enter Edit Mode.
  2. Right-click on the work order or task that you want to modify and select Modify Stop. A calendar window like the one below will appear:

    Modify Start

  3. To change the End Date, click on a new date in the calendar (the selected date is indented).
  4. To change the End Time, click on the time field and type the new time information.
  5. Use the single arrow buttons to modify the month Single Arrow.
  6. Use the double arrow buttons to modify the year Double Arrow.
  7. Click OK when you are finished modifying the date and/or time data.
  8. Click to save your changes. The related Work Order or Task record will be automatically updated.

    Note: You can also reschedule the end date or adjust the ending time for a work order or task by clicking on the last arrow or triangle and dragging it to a new date. The start date will remain the same.

See Also

Work Order Scheduler

Work Order Scheduler Display

Navigation Tools

Modify Range