Excluding Dates

To prevent your PMs from generating Work Orders during a certain date range, complete the following steps:

  1. Click  on the module toolbar to enter Add Mode.
  2. The system will automatically enter the next sequential number in the Exclusion Rec # field.
  3. Enter the dates the exclusion will begin and end. For example, below we've excluded November 26 and 27, 2009 for the Thanksgiving holiday.

    Note: Once you select a date in either date field, the Day of Week field will be disabled.

  4. Enter a Reason if necessary.

    Note: The Modified By and Modified Date fields are auto-populated.

  5. Click to save the record. Your screen will resemble the following:

    Excluding Dates

  6. Click to close the window.

See Also

Exclusion Days

Excluding Days

How Exclusion Days Affect PMs