Toolkit

Android Screenshot

The Work Orders > Tasks > Equipment grid contains the following Toolkit:

Add Cost Markup | Selected Record(s)

Clear Cost Markup | Selected Record(s)

Load Cost Markup(s) from Library | Selected Record(s)

Populate Dates and Hours | Selected Records

Add Cost Markup | Selected Record(s)

Enables the user to create a Cost Markup record and apply it to multiple Equipment Resources on a Work Order.

How to add a Cost Markup to selected Resources

Clear Cost Markup | Selected Record(s)

Deletes all Cost Markup records associated with one or more Equipment Resource records on a Work Order in a single action.

How to clear Cost Markups for selected Resources(s)

Load Cost Markup(s) from Library | Selected Record(s)

Copies established Cost Markups from the Cost Markup Library into multiple Equipment Resources' Cost Markup grids, eliminating the need to repeat the action for each Equipment Resource on a Work Order.

How to load Cost Markup(s) from the Library into selected Work Order Resource(s)

Populate Dates and Hours | Selected Records

Enables a user to record the Dates and Units (hours) that one or more equipment items were used on a Work Order Task without having to open the Equipment resource record(s). This feature is especially useful when a task involves a number of pieces of equipment.

security To run a Toolkit that updates Task Units on Work Order records, you must have the Toolkit - Update Units permission for the Work Orders module.

How to populate Dates and Hours for selected record(s)