If the Resource is a Material or Fluid and is linked to a record in the Parts Inventory then the following rules/special functions apply.
Start Date End Date |
The resource's start and end dates are compared to the selected part's start and end date. The resource's End Date must fall between the part's start and end dates, if they are populated. Note: The Use Part Open Inventory Date Range Parts Integration Work Option must be enabled for this to work. |
Estimated: Unit Cost |
This is automatically filled out with the part's Average Cost. |