Material Resources

The Planned Task module's Material Resources function enables an agency to estimate the amount of a material needed to complete a task and the cost of that material. The quantity and cost information gathered here is rolled up into the Planned Task record's monthly cost estimates.

 

Material Resources grid

A Planned Task record's Material Resources grid lists materials the department expects to use to complete the task this fiscal year.

folder Using Grids >> Add new record Grid Tools>> Android Screenshot Editable Grids>> Web_edit Using Forms >>

 

How to add a Material Resource to a Planned Task

Material Resource record fields

Resource*

Identifies a material that the department plans to use to complete the task.

Unit of Measure

Identifies the material's unit of measurement (for example, feet, meters, items, gross, pounds, tons, etc.).

  • Lucity automatically completes this field using corresponding data from the Material Setup record, if available.

Unit Cost

Specifies the cost to use one unit of this material.

  • Lucity automatically completes this field using corresponding data from the Material Setup record, if available. However, you can change the Unit Cost on this record without altering the original Setup record.

Quantity

Specifies the estimated number of resource units required to complete this task.

  • This value should correlate with the Unit of Measure.

Total Cost

Calculates the total estimated cost of the material required for the task.

  • Calculated as: Unit Cost x Quantity