Excluding Dates
To prevent your PMs from generating Work Orders during a certain date range, complete the following steps:
- Click on the module toolbar to enter Add Mode.
- The system will automatically enter the next sequential number in the Exclusion Rec # field.
- Enter the dates the exclusion will begin and end. For example, below we've excluded November 26 and 27, 2009 for the Thanksgiving holiday.
Note: Once you select a date in either date field, the Day of Week field will be disabled.
- Enter a Reason if necessary.
Note: The Modified By and Modified Date fields are auto-populated.
- Click to save the record. Your screen will resemble the following:
- Click to close the window.