Attaching Open Work Orders to a Standard PM

You may have situations when you need to complete work on an asset prior to the PM generating a Work Order. If you create a Work Order that would typically be generated by a PM, you will want to link the PM to that Work Order. Creating the link in this situation will reset the PM's schedule to the future and not create duplicate work.

Linking a PM to a Work Order can be done from the Work Orders > PM grid. In order for this link to reset the PM's schedule, the link must be created when the Work Order is still open (Status < 950).

*Note: This function only applies to Standard Scheduled PMs. If Tightly Linked PMs are attached to the WO, the Tightly Linked intervals will not update automatically on close of the Work Order. The user will have go into the Tightly Linked interval and manually update it.

How to attach a PM to a Work Order