The second tab of the Observations record appears below. This tab contains additional fields used to rate the observation and defects found. For a description of these fields, refer to the table below:
Field Name |
Description |
Estimated GPM |
The estimated flow rate is a default value assigned from the Inspection Setup table. |
Structure # |
The program automatically assigns the structure number from the Inspection Setup table. |
Cleaning # |
The program automatically assigns the cleaning number from the Inspection Setup table. |
% I/I Removed |
Use this field to record the percent of infiltration and inflow that was removed due to the rehabilitation. |
Remaining GPM |
This field allows you to record the amount of flow remaining after rehabilitation. |
Repaired |
This field allows you to indicate the type of rehabilitation performed. |
User |
These user-defined fields allow you to include additional, custom information. |
Note: In order for the system to calculate the read-only fields below the observation grid, you must enter data into the Defect and Observed (gpm) fields on the Observation tab, and the % I/I Removed field on this tab.