Populate Task Units

The Populate Task Units option allows you to select multiple tasks and update the number of units used to complete them without having to open each individual task record. Upon entering units, the total cost of the task will automatically be updated based on the unit cost and the number of units entered.

To populate units, complete the following steps:

  1. Select the task(s), right click in the grid and select Populate Task Units. The following window will open.

    Populate Units

  2. Enter the number of units used.
  3. Click Button OK.  The task record(s) will automatically be updated.

See Also

Tasks Grid

Adding a Task

Shared Fields

Special Functions

Viewing, Editing, Deleting a Task

Populate Main Task

Populate Dates

Routing Sub-Tasks