The Acceptance tab has a grid to track Structure Vacuum Tests. This grid allow users to track tests that are performed to check to see if a structure was built correctly.
Structure Vacuum Tests grid
This grid contains a list of all Structure Vacuum tests that were performed for the structure.
A sample of the grid appears below. Sort records in each grid by clicking on the headings. An up or down arrow (highlighted in orange below) will appear signifying ascending or descending order. The functions in the grid allow user to view, add, edit, or delete the record.
How To
Add a Structure Vacuum Test
Note: The Structure and Tested Date are required fields. Adding the record this way will auto - populate the Structure field.
Note: For more information about that Structure Vacuum Testing module please go here.