Project Activities tab

This tab is made up of two grids and several fields.

Field

Function

Proj Start Date

The start date of the project.

Proj Est Compl Date

The date the project is expected to the done

Est % Comp By Date

The percentage of the project's estimated duration that is past. Automatically calculated using the following.

  • Proj Est Compl Date - Proj Start Date = # of days for project
  • Current Date - Proj Start Date = # of days past
  • [(# of days past)/(# of days for project)] x 100

Activities Grid

This grid stores a list of all project activities that are attached to the project. These activities can either be added individually, or they can be loaded in sets from the Activities Library module. The records in the grid can be sorted by clicking on a column header (below a sort arrow is highlighted in orange).

Master_Project_activities_grid

Tracking Grid

The second grid is a read - only grid that shows tracking records for any changes made to the dates of a selected activity. It shows these columns

Master_project_activities_tracking

Note: For more information on Activity records and tracking records go here.

How To Add a record to the Activities grid

How To Load records from an Activities Library