This tab is made up of two grids and several fields.
Field
Function
Proj Start Date
The start date of the project.
Proj Est Compl Date
The date the project is expected to the done
Est % Comp By Date
The percentage of the project's estimated duration that is past. Automatically calculated using the following.
Proj Est Compl Date - Proj Start Date = # of days for project
Current Date - Proj Start Date = # of days past
[(# of days past)/(# of days for project)] x 100
Activities Grid
This grid stores a list of all project activities that are attached to the project. These activities can either be added individually, or they can be loaded in sets from the Activities Library module. The records in the grid can be sorted by clicking on a column header (below a sort arrow is highlighted in orange).
Right-click in the grid to add a record
Right-click on an existing record to get a menu with options to View Record, Add Record, Edit Record, Delete Record, or Load from Activities Library.
Double-click on an existing record to open it
Tracking Grid
The second grid is a read - only grid that shows tracking records for any changes made to the dates of a selected activity. It shows these columns
Note: For more information on Activity records and tracking records go here.