Air Test Header Data

The Air Test header contains general information to identify each inspection. The header appears at the top of the module window and remains visible as users navigate through the module's tabs.

header

Field

Function

US Structure*

Specifies the structure at which the pipe begins. Click the caption button or click in the field and hit F9 to bring up a list of pipes from the Sewer Pipe module. If the Alt ID is selected, the US Structure is automatically populated.

DS Structure

Specifies the structure at which the pipe ends. This field is automatically completed when either the US Structure or Alt ID are selected.

Alt Pipe ID

Identifies the pipe's user-defined ID. This field can be used to select the pipe, rather than using the US Structure. Click the field caption button or click in the field and press F9 to bring up a list of pipes from the Sewer Pipe module. If the US Structure is selected, this field is automatically completed.

Project ID

Enables users to link the air test to a project in the Work Project Management system. Click the field caption button or click in the field and press F9 to bring up a list of projects from the Project module.

Note: This field is enabled only if the Integration with Work option is turned on in the Sewer Options module.

Latest Inspection

Indicates whether this test represents the most recent air test for the pipe.

* Required field.