Construction Records Header Data

At the top of the module window you will see header data. This data remains at the top of your screen as you use the tabs to navigate through the record. The header fields are described in the table below:

Field Name

Definition

Project Number

This field allows you to identify the construction project with a unique alphanumeric ID.

Date

Here, you can record the project's beginning date.

Contractor

Designer

Inspector

These alphanumeric fields allow you to record the names of the contractor, designer, and inspector associated with the project.

Note:  In order to save your changes to the record, the Project Number field must be filled in.